Este es un resultado real de nuestro motor, construido a partir de un cronograma sintético de construcción en progreso. Cada campo que ves proviene del análisis real.

43/100

Puntuación de salud del cronograma

Basado en la metodología de evaluación de 14 puntos de DCMA

Necesita trabajo antes de que este cronograma sea confiable
8 aprobadas8 fallidas1 no aplicables
File: Highway Interchange Phase 2
Format: MSPDI XML
Tasks: 312
Data date: 2026-04-15

Summary

This schedule shows moderate-to-serious health issues that will likely cause a late finish without intervention. The most urgent problems: (1) negative float on 14 tasks means the schedule already predicts a late finish mathematically, almost certainly caused by the 11.2% hard-constraint rate overriding the logic network; (2) CPLI of 0.88 is a reliable predictor of project overrun; (3) logic density of 1.74 links per task means the network has widespread open ends beyond what the logic check alone shows, making float unreliable across the board; (4) BEI of 0.91 confirms that slippage is already occurring against the baseline. Priority actions in order: fix the 14 negative-float tasks by tracing back to the constraining dates; close the network open ends identified in the logic and logic density checks; update progress on the 7.7% of missed tasks so the schedule reflects current reality.

🔒 The paid report adds: named offending tasks, exact MS Project fix steps, risk outlook, next-steps close

Detalle de cada verificación

All 17 checks. Free tier shows pass/fail. The paid report adds the offending task list and fix steps for each failure.

Fallido

Logic (missing predecessor/successor)

8.4% of tasks missing a predecessor or successor (threshold: 5%)

Aprobado

Leads (negative lag)

0 relationships have negative lag. Pass.

Aprobado

Lags (positive lag)

4.3% of relationships use positive lag. Within 5% threshold.

Aprobado

Relationship types (Finish-to-Start)

93.7% of relationships are FS type. Above 90% threshold.

Fallido

Hard constraints

11.2% of tasks have hard constraints (threshold: 5%)

Aprobado

High float

3.2% of tasks have float above 44 days. Within threshold.

Fallido

Negative float

14 tasks have negative total float. None allowed.

Fallido

High duration

6.1% of tasks exceed 44 working days (threshold: 5%). Longest: 87 days.

Aprobado

Invalid dates

No tasks with invalid date combinations found.

N/A

Resources / cost

Schedule is not resource-loaded. Check not applicable.

Fallido

Missed tasks

7.7% of baseline-eligible tasks missed (threshold: 5%).

Aprobado

Critical path test

47 tasks on the critical path. Continuous critical path exists.

Fallido

Critical Path Length Index (CPLI)

CPLI = 0.88 (threshold: 0.95). Strong predictor of late finish.

Fallido

Baseline Execution Index (BEI)

BEI = 0.91 (threshold: 0.95). 9% of due tasks are incomplete.

Fallido

Logic density

Average 1.74 links per task (threshold: 2.0). Open ends prevalent.

Aprobado

Merge hotspots

No task with 8 or more predecessors found.

Aprobado

Insufficient detail

No task exceeds 10% of the project span (174 days).