Informe de salud del cronograma de muestra
Este es un resultado real de nuestro motor, construido a partir de un cronograma sintético de construcción en progreso. Cada campo que ves proviene del análisis real.
Puntuación de salud del cronograma
Basado en la metodología de evaluación de 14 puntos de DCMA
Summary
This schedule shows moderate-to-serious health issues that will likely cause a late finish without intervention. The most urgent problems: (1) negative float on 14 tasks means the schedule already predicts a late finish mathematically, almost certainly caused by the 11.2% hard-constraint rate overriding the logic network; (2) CPLI of 0.88 is a reliable predictor of project overrun; (3) logic density of 1.74 links per task means the network has widespread open ends beyond what the logic check alone shows, making float unreliable across the board; (4) BEI of 0.91 confirms that slippage is already occurring against the baseline. Priority actions in order: fix the 14 negative-float tasks by tracing back to the constraining dates; close the network open ends identified in the logic and logic density checks; update progress on the 7.7% of missed tasks so the schedule reflects current reality.
Detalle de cada verificación
All 17 checks. Free tier shows pass/fail. The paid report adds the offending task list and fix steps for each failure.
Logic (missing predecessor/successor)
8.4% of tasks missing a predecessor or successor (threshold: 5%)
Leads (negative lag)
0 relationships have negative lag. Pass.
Lags (positive lag)
4.3% of relationships use positive lag. Within 5% threshold.
Relationship types (Finish-to-Start)
93.7% of relationships are FS type. Above 90% threshold.
Hard constraints
11.2% of tasks have hard constraints (threshold: 5%)
High float
3.2% of tasks have float above 44 days. Within threshold.
Negative float
14 tasks have negative total float. None allowed.
High duration
6.1% of tasks exceed 44 working days (threshold: 5%). Longest: 87 days.
Invalid dates
No tasks with invalid date combinations found.
Resources / cost
Schedule is not resource-loaded. Check not applicable.
Missed tasks
7.7% of baseline-eligible tasks missed (threshold: 5%).
Critical path test
47 tasks on the critical path. Continuous critical path exists.
Critical Path Length Index (CPLI)
CPLI = 0.88 (threshold: 0.95). Strong predictor of late finish.
Baseline Execution Index (BEI)
BEI = 0.91 (threshold: 0.95). 9% of due tasks are incomplete.
Logic density
Average 1.74 links per task (threshold: 2.0). Open ends prevalent.
Merge hotspots
No task with 8 or more predecessors found.
Insufficient detail
No task exceeds 10% of the project span (174 days).
Ready to fix your schedule?
Drop your own file and get a free score in about 10 seconds.
Score my schedule free